Government changes jeopardize road infrastructure projects, leading to costly renegotiations.
Public-private partnerships for road infrastructure often lead to renegotiations of contracts. In Portugal, these renegotiations are mainly caused by government changes, environmental issues, delays in land acquisition, and lower than expected traffic. These renegotiations can result in compensation from the government or significant changes to the contract, affecting the original risk allocation.